TISHREEN Dam Power Plant

MANBEJ, ALEPPO, 1994 - 1997

Owner: Ministry of Irrigation

Main Contractor: General Company for Land Reclamation

Project Description:


Concrete dam on EUPHRATES river at the end of Al-ASSAD lake.

6 water turbines with total capacity of 600 MW Hydropower dam.

It consists of 3 sections: upper-stream, downstream and Powerhouse.


TOEC contract is to execute 110,000 m3 of reinforced concrete, which is 40% of the entire project divided to:         

- Downstream area of 36 m height.

- Slope protection with reinforced concrete for the inlet and outlet water canal.


:: Our Projects

Browse by type:

Browse by country:

Browse all

You can find T.O.E.C